New noise walls for Gladstone Park

5 April 2017

Work to replace existing noise walls will start in two weeks

Gladstone Park noise walls 

Work is about to commence to install new noise walls on the Gladstone Park side of the Tullamarine Freeway.

After trees and vegetation were cleared, the foundations for the new walls were laid, and construction is scheduled to begin within the next fortnight.

In some cases, we'll require access to properties adjacent to the freeway in order to demolish the old noise walls and install the replacements.

We've now contacted all affected residents with the relevant information.

While the replacement process is expected to take between three and four months, we'll only need access to individual properties for around two days each.

Existing noise walls on the Tullamarine side of the freeway will be replaced later in the year, and impacted residents will be notified before works commence.

Late last year, we held a couple of information sessions in the Gladstone Park area about the new noise walls. If you missed out, you can watch one of the sessions here.

This noise wall replacement is part of the Mickleham Road interchange upgrade.